MonoSync using docker-swarm on high availability infrastructure. In the below table described how many servers must be deployed for high availability in datacenter infrastructure.

Single Data Center

Server Count(Min)

DataCenter Site

Operational Site

Information

2

Active DataCenter

Production

All MonoSync Services

Multiple Data Center

Server Count(Min)

DataCenter Site

Operational Site

Information

2

Active DataCenter

Production

All MonoSync Services Installation

2

Passive DataCenter or Disaster Recovery-Site

Production

All MonoSync Services Installation

If redundancy is also required for each DataCenter minimum server count must be is two(2).